Analysis of Price Adjustment Payments for RCC T-Beam and Pre-stressed Bridges Construction Contracts

Main Article Content

Navneet Chaudhary
A. K. Mishra
Aithal P. S.

Abstract

Purpose: Let’s compare and analyze the price adjustment payments for RCC T-beam and Pre-stressed bridges construction contracts for evaluation of the cost effectiveness of price adjustment payment.


Design/Methodology/Approach: Based on Questionnaire survey and Official documents, comparison and analysis were done for RCC T-beam and Pre-stressed bridges construction contracts of price adjustment payment.


Findings/Result: The weightage of price adjustment payment is 9% of total payment. This assessment was done to show the importance of price adjustment and its study in bridge construction contracts. As per GCC & SCC clause 53.7 of Standard Bidding Document, price adjustment is limited to 25%. Comparison of payments for price adjustments was done for different T-girder and pre-stressed bridges. Price adjustment payments for the computed price adjustment coefficients were calculated and compared with that of the actual payment made.


Originality/Value: This research was mainly dedicated to deriving logical price adjustment coefficient ranges in making the price adjustment process for RCC T-girder and prestressed construction contracts economical.


Paper Type: Research paper

Article Details

How to Cite
Navneet Chaudhary, A. K. Mishra, & Aithal P. S. (2023). Analysis of Price Adjustment Payments for RCC T-Beam and Pre-stressed Bridges Construction Contracts. International Journal of Case Studies in Business, IT and Education (IJCSBE), 7(1), 141–163. https://doi.org/10.47992/IJCSBE.2581.6942.0250