Evaluating the Impact of Disputes on Time and Cost of Projects

Main Article Content

A. K. Mishra
P. S. Aithal

Abstract

Purpose: Noise of impacts exists and it is essential to assure the significance factors. The study evaluates the impact of disputes on time and cost of road projects.


Design/Methodology/Approach: Based on Extension of earlier research 45 factors were identified using Literature Review and Case study followed by Questionnaire, Key Informant Interview. The Test Hypothesis for Significant impact was done using F-test.


Findings/Result: Complete time lost during the interaction would be about 37 years and a half year till date. Normal time lost 4 years and 8 months and 7 days for each undertaking.


The debates, which have not been addressed, couldn't be surveyed. The aggregate sum spent on ADR just, for eight undertakings was 38 needs and 5 thousand, on the normal expense for a solitary venture was 4 lakhs and 76 thousand. In any case, the all-out cost caused couldn't be assessed until the debates have been totally settled. This cost included just Settlement/referees or the two charges different costs, for example, opportunity misfortunes and guaranteed cost are excluded. The serious issue that emerges because of debates is time invaded and cost overwhelm.


Originality/Value: The professionals assumed to get insights to create zero dispute projects based on real time cases.


Paper Type: Research paper

Article Details

How to Cite
A. K. Mishra, & P. S. Aithal. (2023). Evaluating the Impact of Disputes on Time and Cost of Projects. International Journal of Applied Engineering and Management Letters (IJAEML), 7(1), 15–27. https://doi.org/10.47992/IJAEML.2581.7000.0165
Section
Articles

Most read articles by the same author(s)

<< < 2 3 4 5 6 7 8 9 10 11 > >>